TORmem · Ninh Bình Data Center Campus
Mỹ Thuận Industrial Park · Mỹ Lộc ward

Ninh BìnhAI & Cloud Data Center Campus

A 30 MW Tier III campus in the Mỹ Thuận Industrial Park, built in three 10 MW phases on cleared, flood-free land about 80 km from Hanoi. Two 110 kV substations sit within 2 km of the site, and power at the factory tariff is among the cheapest in Asia.

IT capacity by phase

30MW · three 10 MW phases
Phase 1 · 10 MW≈ month 32 Phase 2 · 20 MW total≈ month 44 Phase 3 · 30 MW total≈ month 56

Each phase starts only when its capacity is contracted.

Campus
3 × 10 MW
Grid nodes
2 × 110 kV
Grid need
≈44 MVA
To Hanoi
≈80 km
Target PUE
≤ 1.4
Land
2.5–3 ha, ready
Top-down site plan rendering: data hall buildings in a row with rooftop solar, the utility yard behind them, solar carports along the road
TORmem campus design, site plan · concept, shared with the Da Nang and Gia Lai campuses
The campus concept

One hall opens; two more follow on contract

  • Hall 1 · Phase 110 MW, liquid-ready for AI racks, with rooftop solar.
  • Halls 2 and 3Pads and corridors reserved; built when capacity is signed.
  • On-site 110/22 kV substationTwo 63 MVA transformers, fed from Mỹ Thuận and Hiển Khánh.
  • Rear utility yardN+1 generators, 48 h of fuel and UPS rooms behind each hall.
  • Two fiber entriesSeparate duct routes from two carriers, entering on opposite sides.
The opportunity

An AI-ready campus at the edge of the Hanoi market

Hanoi is Vietnam's government, banking and AI hub, but land and grid capacity near the capital are scarce. Mỹ Thuận offers what Hanoi cannot: cleared land ready to hand over, two 110 kV substations within 2 km, a factory power tariff of about US$0.073 per kWh and road access to the capital in under two hours.

The engineering basis matches TORmem's Da Nang, Gia Lai and Quang Trung campuses: Tier III concurrent maintainability, 2N UPS, diverse fiber and a staged, demand-led build.

Feasible, subject to five critical gates

Power, land and incentives are favourable. Three issues decide the project: data centers must be added to the park's permitted industries, EVN must commit a dedicated 110 kV supply instead of the 22 kV offered, and a second carrier must bring diverse fiber. Proceed to a 4–9 month bankable feasibility phase that closes these before final investment.

Lead developerTORmem (California, USA)
Project companyVietnamese project company; data center services carry no foreign-ownership cap under the 2023 Telecommunications Law
Land termsOne of six 2–3 ha plots, sub-leased from the park developer; one-time payment of US$110–125/m² to 30 September 2071
IT capacity30 MW in three phases of 10 MW, each triggered by contracted demand
Grid connectionDedicated 110 kV supply to an on-site 2 × 63 MVA substation; full campus needs about 44 MVA
ReliabilityTier III, concurrently maintainable, as a minimum
Facility investmentUS$88–99 million for Phase 1, including land; US$212–239 million for 30 MW
TimelinePhase 1 ready about month 32; full 30 MW about month 56
01 / 04

Why Ninh Bình, and why Mỹ Thuận

≈80 km

Close to Hanoi

The park sits on National Roads 21 and 21B, with links to Road 10 and the North–South Expressway. Hanoi is about 80 km away; Hai Phong port and Nội Bài airport about 100 km.

2 substations

110 kV within 2 km

Hiển Khánh 110 kV (2 km, about 63 MVA spare today) and the new Mỹ Thuận 110 kV (0.2 km, 2 × 63 MVA, in service Q3 2027). EVN Ninh Bình has committed 180 MW to the park.

Ready land

Cleared and flood-free

Six plots of 2–3 ha are cleared, levelled and ready to hand over, with no recorded flooding. The park covers 158.6 ha and is about 56% occupied.

US$0.073

Low-cost power

From 1 November 2026 the factory tariff above 35 kV averages about VND 1,879 per kWh around the clock, roughly half Malaysia's and a quarter of Singapore's commercial rates.

Special

Top-tier incentives

Under the Digital Technology Industry Law 71/2025, AI data centers are a specially encouraged sector. GPU servers, UPS and chillers may be exempt from import duty.

5,000 m³

Water and wastewater

Two water plants supply 5,000 m³ per day at about US$0.60/m³. The wastewater plant takes 5,000 m³ per day today and is licensed for 15,000.

TORmem campuses

Where Ninh Bình fits

Da Nang leads on subsea cables, Gia Lai on raw power. Ninh Bình is the northern campus: cheap power and ready land within reach of Hanoi's banks, government suppliers and AI companies.

Ninh Bình · Mỹ Thuận IPDa Nang Hi-Tech ParkGia Lai campus
Site2.5–3 ha in a working industrial parkAbout 2.5 ha in the Hi-Tech Park3–5 ha greenfield parcel
Land termsOne-time payment, US$110–125/m², to 207150-year lease; land-rent exemption requestedRent at a discount to market
Phase 1 IT10 MW10 MW10 MW
Campus30 MW (3 × 10 MW)30 MW (3 × 10 MW)40 MW (4 × 10 MW)
GridTwo 110 kV substations within 2 km; about 44 MVA neededDedicated 110 kV; about 44 MVA220 kV node; about 57 MVA
ConnectivityDomestic backbone to Hanoi; only VNPT at the gate todayAPG and ALC land in the cityADC and SJC2, Quy Nhơn
WorkloadsAI inference and training near Hanoi, data residency, disaster recoveryAI anchor, sovereign cloud, DR, colocationAI training for an anchor
Main open issuePark zoning must add data centersHigh-tech classificationGrid upgrade timing
Ready for service≈ month 32≈ month 32≈ month 36
02 / 04

Three 10 MW phases, built as demand is signed

Phase 1 builds the site platform, the 110 kV substation for the full campus, the operations building and the first 10 MW hall. Each later phase adds a self-contained hall with its own generators, UPS and cooling.

  1. Phase 1
    10 MW

    Hall 1, liquid-ready for AI racks. Carries the shared works: substation, platform, fiber entries, operations building and meet-me rooms.

    ≈ month 32 · anchor signed for 4–5 MW
  2. Phase 2
    +10 MW

    Hall 2 with its generators, UPS and cooling, added without interrupting Phase 1.

    ≈ month 44 · starts at 70% of Phase 1 leased
  3. Phase 3
    +10 MW

    Hall 3 and matching plant; the campus is complete. Neighbouring land can be held for later growth.

    ≈ month 56 · 30 MW total

Roads, security, water, fiber ducts and substation bays for all three phases are reserved on day one. Capital for Phases 2 and 3 is released only when that capacity is contracted.

Market fit

Who the campus serves

CustomerShareContract
Anchor AI or GPU cloud40–50%5–10 years, take-or-pay; a Hanoi AI company, a regional GPU cloud or a telco's AI service
Enterprise and data residency≈25%3–5 years; Hanoi banks, insurers and government suppliers that must keep data in Vietnam
Disaster recovery10–15%1–3 years; a second site outside Hanoi's grid and flood zone
Retail racks and cages≈10–15%1–3 years; Red River Delta manufacturers and software firms

Target mix for each 10 MW phase. There is no data center in the park yet, so the anchor customer must be signed before financial close.

AI and standard halls

About 30% of each hall is a liquid-cooled zone for 40–80 kW GPU racks. The rest serves 10 kW cloud and enterprise racks with contained air cooling. The anchor's hardware sets the final split.

Commercial model

Customers reserve kW on long contracts and pay a fixed monthly capacity fee. Electricity is metered and billed at EVN cost times PUE, so customers carry power-price risk and the capacity fee repays the debt.

Competitive edge

Against Hanoi sites: available land and 110 kV capacity. Against Johor: a similar rent but power about 40% cheaper, data kept in Vietnam, and a 1–2 ms link to Hanoi users.

Proposed fees

Priced at Johor levels, with cheaper power

Proposed prices excluding VAT, at USD 1 = VND 25,800. A cost-based price for Ninh Bình is US$116–187 per kW per month before power, depending on build cost, return and occupancy; the list price sits near the low end to compete with Johor.

ServiceUS$VNDTerms
Wholesale capacity, anchor (2 MW+)120–140 / kW / month3.10–3.61M / kW / month5–10 years, take-or-pay; list price US$130
High-density GPU capacity150–170 / kW / month3.87–4.39M / kW / month5–10 years; premium pays for liquid cooling
Private suite or cage (100–500 kW)160–190 / kW / month4.13–4.90M / kW / month3–5 years
Power, factory tariff≈69–74 / kW / month≈1.8–1.9M / kW / monthEVN tariff × PUE + 5% handling, metered monthly
Power, if business tariff applies≈106–114 / kW / month≈2.7–2.9M / kW / monthAbout 54% more; tariff class to be confirmed by EVN
Retail rack (42U, 5 kW, power included)≈800 / month20.6M / month1–3 years
Cross-connect≈100 / month2.6M / monthPer connection
Remote hands≈50 / hour1.3M / hourFirst 2 hours a month free for wholesale customers

Wholesale rent before power, by market

US$ per kW per month (= US$ thousand per MW per month) · CBRE and market sources, 2026

Singapore403 Hong Kong295 Tokyo280 US, 250–500 kW205 Sydney188 US, 3–10 MW175 N. Virginia, 10 MW+160–185 Johor110–150 Ninh Bình, list130 Mumbai78–100

Ranges shown at midpoint. No consultant publishes a wholesale rent for the Gulf; UAE retail power add-ons run about US$270–680 per kW, and Saudi operators earn about US$2–3 million per MW a year.

Revenue per phase
$13.3M
8.5 MW leased × US$130
EBITDA per phase
≈$10.6M
Power passed through at cost
Full campus EBITDA
≈$32M
30 MW, 85% leased
Return on capital
≈14%
On US$226M midpoint
Sensitivity

If the build costs Turner & Townsend's Vietnam index of US$8.32 per watt instead of TORmem's US$7.0–7.8 million per MW, the return falls to about 11%. If EVN applies the business tariff, the all-in price rises by about US$40k per MW per month and competes less well with Johor.

The site

2.5 hectares hold all three phases

Three two-storey halls sit side by side, with the utility yard behind them, the substation at the end nearest the Mỹ Thuận 110 kV station and the operations building facing the park road.

Three data halls (2 storeys)

9,000 m²

3,000 m² footprint per hall · Phase 1 built, Phases 2 and 3 reserved

Substation and utility yard

4,500 m²

110/22 kV substation, generators, fuel and water tanks, UPS rooms

Heat rejection

3,000 m²

Chillers, dry coolers and, once water is confirmed, cooling towers

Operations building

1,500 m²

Lobby, network operations center, two meet-me rooms, offices

Roads, security and landscaping

7,000 m²

Ring road, loading dock, parking, guardhouse, drainage and setbacks

Site rules and requirements

  • Planning limits: 60–70% site coverage, a floor-area ratio of 0.6–3.5 and no fixed height limit, so two-storey halls fit easily.
  • Candidate plots: CN3-2, CN5-2, CN11-1, CN12-1, CN12-2 and CN12-3; a plot near the Mỹ Thuận substation shortens the 110 kV line.
  • Expansion: ask the park for first refusal on the neighbouring plot for growth beyond 30 MW.
  • Generators, fuel tanks and rooftop plant: the park has not yet confirmed these are allowed; get written approval.
  • Geotechnical survey is the investor's responsibility. The park does not normally allow surveys before signing, so negotiate access in the MOU.
  • Floor level raised above the local flood line even though the site has no recorded flooding.

Areas are planning estimates. The final layout follows the surveyed plot and the anchor customer's requirements.

03 / 04

The Tier III design basis

Availability

Tier III minimum

Concurrently maintainable; Uptime design and constructed-facility certification, 99.982% target.

Power

On-site 110 kV substation

Two 63 MVA transformers, N+1, fed from two 110 kV stations; A/B paths; 2N Li-ion UPS.

Standby power

N+1 generators

2.5–3 MVA diesel or HVO sets with 48 hours of fuel on site.

Cooling

Air, liquid and water

Chillers with economizers for cool winters; direct-to-chip loops for AI racks.

Network

Two carriers

VNPT plus a second carrier, Viettel or FPT, on physically separate routes to Hanoi.

Resilience

Storm-rated envelope

Roof, façade and plant rated for Red River Delta typhoons; raised floor level.

Security

Five layers

On top of the park's guards, police liaison and 24/7 road CCTV: own fence, biometrics, CCTV; ISO 27001.

Fire

Park brigade on site

Two fire trucks and a dedicated fire main at 80 m head and 360 m³/h, plus in-hall gas suppression.

Power · supplier EVN Ninh Bình

The power is nearby; the connection must be 110 kV

EVN Ninh Bình has offered 22 kV lines to the plot fence. At PUE 1.4, 30 MW of IT draws about 44 MVA, far more than 22 kV feeders should carry. The campus needs its own 110/22 kV substation fed from both Mỹ Thuận and Hiển Khánh, built once in Phase 1 for all three phases.

Grid demand as each phase is added

MVA at power factor 0.95 and PUE 1.4, against spare capacity at Hiển Khánh today and the firm capacity of the on-site substation

010203040506070 MVA P1P2P3 30 MW campus ≈ 44 MVA On-site substation, firm N+1: 63 MVA Cumulative demand per phase: 14.7 · 29.5 · 44.2 MVA

Hiển Khánh has about 63 MVA spare today (2 machines, 40% loaded). Mỹ Thuận 110 kV adds 2 × 63 MVA from Q3 2027, before Phase 1 is ready. Other park tenants also draw on both stations, so EVN must confirm how much is already promised.

IT load
30 MW
Three 10 MW phases
Facility demand
39–42 MW
PUE 1.3–1.4
Grid demand
41–44 MVA
At power factor 0.95
Annual energy at 80%
≈294 GWh
≈US$21M a year at the factory tariff

Grid today

  • Hiển Khánh 110 kV, two transformers totalling about 103 MVA, 2 km from the park, about 40% loaded.
  • Mỹ Thuận 110 kV, 2 × 63 MVA, 0.2 km from the park, under construction; completion December 2026, in service Q3 2027. It is in the revised Power Development Plan VIII.
  • No dry-season cuts. The park says the area has priority supply and has not been curtailed in dry seasons.
  • Cost split: EVN pays for lines to the plot fence; the investor builds the substation on its own plot and contracts directly with EVN Ninh Bình.
  • Tariff from 1 November 2026: factory rate above 35 kV is VND 1,792 normal, 1,123 off-peak and 3,218 peak per kWh. Peak is 17:30–22:30, Monday to Saturday; off-peak is 00:00–06:00.

Renewable supply

The park allows rooftop solar on the plot, and the design carries solar on every hall roof and carport. For larger volumes, a direct power purchase agreement over EVN's grid can supply renewable energy with traceable certificates.

What EVN must confirm

  1. Load forecast

    Demand by phase submitted to EVN Ninh Bình: 15, 30 and 44 MVA. The park will arrange the meeting.

  2. Capacity letter

    About 44 MVA at 110 kV from two stations, signed by EVN and the park management board, before the land deal becomes unconditional.

  3. Connection agreement

    Line route from Mỹ Thuận and Hiển Khánh, asset ownership, energization date and EVN approval of the substation design.

  4. Tariff class

    Written confirmation of the factory tariff, not the business tariff, which costs about 54% more around the clock.

Connectivity · the weakest link today

One carrier at the gate; a second is essential

VNPT has built underground ducts to the plot fence, and two independent routes are possible through VNPT. A data center needs a second carrier on a separate route, and international capacity reaches the north over the domestic backbone from landings in Da Nang and Quy Nhơn.

Indicative round-trip latency

Milliseconds, estimate · about 10 µs per km of fiber round trip, before equipment delay

Hanoi1–2 ms Da Nang (APG, ALC)8–10 ms Quy Nhơn (ADC, SJC2)11–13 ms Ho Chi Minh City13–16 ms Hong Kong20–25 ms Singapore30–40 ms

Scale 0–40 ms; lighter segment shows the upper end of the range. Estimates only: the park will answer on latency and international bandwidth after meeting the carriers.

Network plan

  • VNPT, already at the park gate with ducts to each plot: first route.
  • Viettel or FPT on a physically separate route, entering on the opposite side of the plot: required before final investment.
  • Hanoi interconnection at a carrier-neutral Hanoi data center for cloud on-ramps and peering.
  • International paths through two different landing cities, so one cable fault does not cut service.
Cable risk

In August 2026 four international cables serving Vietnam were impaired at the same time, including SJC2 and AAE-1. Contracts should require capacity on at least two cable systems and a service level that covers cable cuts.

Cooling and climate

Cool winters help; water is available

The Red River Delta has hot, humid summers near 35°C but cool winters that give economizer hours from December to March. With 5,000 m³ of water a day available, evaporative cooling is an option here, unlike in water-limited sites.

OptionFit for Ninh BìnhUse on this campus
Air-cooled chillers with economizersWorks year-round; free cooling in winter; low water useBase cooling, 10 kW racks
Direct-to-chip liquid (CDU loop)Handles 40–80 kW racks; warm return water extends economizer hoursAI zone, ≈30% of each hall
Evaporative cooling towersMost efficient; park water supply of 5,000 m³/day, discharge temperature limits applyIf the water letter confirms supply
ImmersionHighest density; specialist supply chainPilot only, if a tenant asks

The park has not yet answered whether liquid cooling and water-treatment chemicals face any limits; this goes into the data-room questions.

04 / 04

Land, investment and the path forward

The plot is sub-leased from the park developer for a one-time payment that fixes the land cost to 2071. There is no land-rent exemption, because the land is paid upfront, but the total is small next to the building cost.

TermOffered by the park
LessorPark infrastructure developer (sub-lease); land lease decision signed by the Ninh Bình People's Committee
Area2.5–3 hectares from six suitable plots
PriceUS$110–125 per m², one payment (Q4 2026); about US$2.8–3.8 million in total
Running feeUS$0.70 per m² per year for management and infrastructure upkeep
TermTo 30 September 2071, about 45 years; extension depends on state policy then
ZoningGate Data centers (VSIC 6310) are not in the park's permitted industries; the park's planning must be amended
LicensingInvestment certificate within 3 days of a complete file if the developer prepares it; construction permit from the park management board
MOUNo deposit; land held for 3 months; deposit refunded if power, water or roads are late
FinancingLand rights cannot be mortgaged to banks that are not licensed in Vietnam
DisputesVietnamese courts; international arbitration not accepted so far

What Ninh Bình gains

  • Investment. US$212–239 million of facility investment over three phases, the park's first data center.
  • Digital infrastructure. A new 110 kV substation, carrier-neutral meet-me rooms and diverse fiber that other tenants can use.
  • Skilled jobs. About 40–60 permanent staff per phase, with 250–400 construction workers at peak, trained with regional universities and FPT's planned Nam Định campus.
  • A northern digital hub. AI and backup capacity for Hanoi on Ninh Bình land, supporting the province's high-tech industry goals.
Export controls

An anchor customer's U.S.-origin AI hardware may need export authorization. The park could not yet advise on GPU import procedures, so export counsel, vendor confirmation and any licence come before hardware commitments.

Indicative facility investment

US$ million · including land, excluding customer IT hardware and financing costs

Phase 1 · 10 MW88–99 Each later phase62–70 20 MW150–169 Full 30 MW212–239

Scale 0–240. TORmem's basis of about US$7.0–7.8 million per MW, plus US$2.8–3.8 million for land. Phase 1 carries the substation, 110 kV line, platform and operations building. Includes about 11% contingency; to be refined by a quantity surveyor at concept design.

RiskImpactMitigation
Park zoning not amended for data centersCriticalAmendment approved before any land payment; MOU conditional on it
EVN offers only 22 kV, or 110 kV lateCriticalCapacity letter at 110 kV before land deal; Phase 1 tied to Mỹ Thuận station in service
No anchor customerCriticalNo financial close without a signed anchor for 4–5 MW
Single carrier at the gateHighSecond carrier contract and separate route before final investment
Business tariff appliedHighWritten tariff class from EVN; customers carry power cost under pass-through
Financing limits and court-only disputesMediumLenders licensed in Vietnam; negotiate arbitration in the investor agreements
Typhoon and floodingMediumNo recorded flooding; raised floor level and storm-rated envelope
Later phases not contractedMediumPhases 2 and 3 built only at 70% of the prior phase leased

Phase 1 is ready about month 32; the full 30 MW about month 56

Indicative schedule, months from signing the MOU · Phases 2 and 3 start only on contracted demand

01224324456 Months from signing the MOU MOU and data room0–1 Park zoning amendment1–6 Fatal-flaw diligence1–3 Concept and anchor alignment2–5 Bankable feasibility (FID)4–9 Design and procurement8–14 Phase 1 build and commissioning14–32 Phase 1 ready for serviceMonth 32 · 10 MW Phase 2 · 20 MW total32–44 Phase 3 · 30 MW total44–56

The zoning amendment period is an estimate; the park has not given a timeline. The MOU's 3-month land hold should be extended to cover it.

Working together

Eight gates before final investment

Proceed to a 4–9 month bankable feasibility phase. No construction notice or unconditional land or capital commitment until these are met.

  1. 01 · MOU

    Land hold and data room

    MOU on one of the six plots, with the hold extended past the zoning amendment, plus plot maps, utility drawings and draft sub-lease.

  2. 02 · Zoning

    Data centers permitted

    The park's planning amended to add data centers (VSIC 6310), approved in writing by the province.

  3. 03 · Power

    EVN 110 kV letter

    About 44 MVA at 110 kV from Mỹ Thuận and Hiển Khánh, co-signed by EVN Ninh Bình and the management board, with the tariff class.

  4. 04 · Network

    Second carrier

    Viettel or FPT on a separate route, latency tests to Hanoi and international capacity on two cable systems.

  5. 05 · Site

    Plot studies

    Geotechnical and topographic surveys, flood review, written water and wastewater letters, and approval for generators and fuel.

  6. 06 · Incentives

    AI data center status

    Written confirmation of incentives under Law 71/2025 and Decree 353/2025, corporate tax treatment and the import-duty equipment list.

  7. 07 · Customer

    Anchor letter of intent

    An anchor for 4–5 MW of Phase 1, with authorized hardware supply and end-use approvals.

  8. 08 · Economics

    Bankable model

    Cost plan within ±5%, equipment quotes, onshore financing, tax opinion and a downside test at the business tariff.